A full maintenance grading round is to commence week starting 30th September. This will include reinstating table drains, offlet drains and table drain blocks in preparation for the wet season.

Carveth and Williams roads are in the process of being regravelled with an order raised for a section of Chibnall road to be regravelled as soon Williams road is finished.

1000 guideposts have been received and will be installed primarily on culverts in the first instance.

All shoulder repairs have been completed in preparation for the reseal to begin in November. Patching has been completed on the majority of the roads for reseal.

Please report any damage to roads or signs to Council.