Round 1 of the maintenance grading program is scheduled to start on October 1st.
Undertaken by Hawke Earthmoving.
Activity Description:
Light formation grading on pavement and shoulders of unsealed roads- with added water
Roads to be undertaken in the following order.
Keleson Rd – 1.5 km | Horsenel Rd – 3.4 km |
Lambert Rd - .5 km | Hughes Rd -1.5 km |
Sandy Rd – 1.4 km | Guys Creek Rd -1.6 km |
Whitstone Rd – 2.3 km | Macato Rd – 3.3 km |
Acacia Gap Rd – 1.5 km | Leonino Rd – 3.3 km |
Chibnall Rd – 7.0 km | Notta Rd – 1.0km |
Parkin Rd – 2.2 km | Brougham Rd – 4.5 km |
Duddell Rd - .6 km | Duncan Rd – 2.8 km |
Letchford Rd – 5.5 km | Meade Rd – 1.5 km |
Spencer Rd – 3.6 km | Trenow Rd - .1 km |
Lawnton Rd – 1.0 km | Stockwell Rd – 1.2 km |
Mira Rd – 1.5 km | Aldridge St – 1.2 km |
Austin St – 1.0 km | Collet St – 1.0 km |
South Tce - .25 km | Barrow St - .5 km |
Musgrave St - .5 km | Cherry St - .8 km |
Reed beds Rd - .2 km | Carveth Rd - .6 km |
William Rd – 1.3 km | Cyress Rd - .5 km |
IIII Rd – 1.0 km | Pipeline Rd – 1.2 km |
Santo Rd – 1.1 km | Kentish Rd – 3.2 km |
Livingston Rd – 1.8 km | Oxford Rd – 1.2 km |
Middle Arm Rd – 6.2 km | Bees Creek Rd – 1.5 km |