Works have begun to address Shoulder drop off issues before resealing roads. Below is only an estimated timeframe from the contractor for completion:
Wallaby Holtze Road (Northern Area) (17/08 - 18/08) | 2 Days |
Thorngate Road (Northern Area) (19/08 - 25/08) | 5 Days |
Thorak Road (Northern Area) (25/08 - 26/08) | 2 Days |
Wagtail Court (Howard Springs) (29/08) | 1 Day |
Stanley Road (Howard Springs) (30/08) | 1 Day |
Woodcote Crescent (Girraween) (31/08) | 1 Day |
Banker Road (Herbert) (01/09) | 1 Day |
Trepang Road (Herbert) (02/09 - 05/09) | 2 Days |
Sunter Road (Herbert) (06/09 - 07/09) | 2 Days |
Koro Road (Herbert) (08/09) | 1 Day |
Morgan Road (Virginia) (09/09) | 1 Day |
Shrike Lane (Humpty Doo) (12/09) | 1 Day |
Hayball Road (Humpty Doo) (13/09) | 1 Day |
Brahminy Road (Humpty Doo) (14/09 - 15/09) | 2 Days |
It is intended that the reseal contractor will commence work next week (week beginning 22/8/16)
Working in the following order:
South west area Old Bynoe Rd / Mira Rd South / Reedbeds.
Northern area Wallaby Holtz Rd / Thorngate Rd / Thorak Rd / Phoebe Rd.
Howard sprigs area Corella Ave / Wagtail Crt / Stanley Rd / Westall Rd.
Girraween area Woodcote Cres / Gosport Rd.
Herbert area Banker Rd / Trepang Rd / Sunter Rd / Koro Rd.
Virginia area Morgan Rd /Brooking Cct / Sayer Rd.
Humpty Doo area Shrike Ln / Hayball Rd / Brahminy Rd / Trippe Rd / Freds Pass Rd.
Please obey all traffic management.